Simplifying Cambridge, MA Building Permit Fees 2025

Navigating permit fees in Cambridge doesn’t need to be confusing. Use this streamlined guide to see what you’ll pay and what to watch out for, including small residential exemptions and when fees triple.

Cambridge skyline with active construction site representing permit fees

At‑a‑Glance Fee Highlights

  • New construction & repairs/alterations: $20 per $1,000 of construction cost (or fraction), minimum $50.
  • Small residential exemption: Projects with ≤3 dwelling units: $15 per $1,000 (minimum $50).
  • Plan amendments, demolition, and foundations: Same rate and small‑residential exemption structure.
  • Sheet metal work: $50 flat + $25 per 100 linear feet.
  • New signs: $10 per $100 of sign cost (rounded up), minimum $20.

Key Fee Details

Permit / Item Fee Structure
Construction & Alterations $20 / $1,000 (min $50); $15 / $1,000 for ≤3 units
Plan Amendments, Demolition, Foundations Same as above
Sheet Metal $50 + $25 per 100 linear ft
New Signs $10 per $100 of sign cost (rounded up); min $20
Certificates of Occupancy (Residential) $100 first unit + $50 each additional
Certificates of Occupancy (Commercial) $100 + $50 per 1,000 sq. ft.
Certificates of Inspection (by occupancy/use) Varies: e.g., Assembly (A): $50 up to 50 occ. + $2/occ. over; R‑1: $50 + $5/room over 10; R‑2/R‑4/R‑5: $100 + $5/unit; Fire escapes $100 each (some exceptions)
Signs (Annual Inspection) $10
Re‑inspections of Code Violations $25
Moving Buildings $15 / $1,000 (rounded up), min $50
Building License $50 initial two‑year license; renewal $50; after two years + 30 days: $60 + $10 per additional late year
Subsidized Dwellings Inspection $100
Plan Review $100, or $50 when included in a building permit

When Does the Fee Triple?

Starting construction before obtaining a permit? The standard fee is tripled, per City Ordinances 15.04.010, 15.08, and 15.12. This penalty applies to building, electrical, or plumbing work and paying it doesn’t exempt you from code compliance or other penalties

Not sure which Cambridge fee applies? Get a quick answer.

Frequently Asked Questions (FAQ)

Most permit types carry a $50 minimum fee, even if the computed fee based on cost is less.

Yes projects for three dwelling units or fewer benefit from a reduced rate of $15 per $1,000 (minimum $50) instead of $20 per $1,000.

The required fee will be tripled. It’s best to apply before starting any work to avoid penalties.

Varying scales account for differences in project size, impact, and administrative requirements, especially in certificate and occupancy processes.

$15 per $1,000 of cost, rounded up to the next thousand, with a $50 minimum.

Visit the City’s official page for current fees: Cambridge Building Fees .

Pro Tips

  • Use the small‑residential rate when your project qualifies (≤3 units) to lower costs.
  • Round‑up logic on sign fees means budgeting conservatively avoids surprises.
  • Book inspections promptly to avoid re‑inspection fees and delays.
  • Never start work before the permit is issued tripled fees add up fast.